ECC6.0- Looking for a way to schedule background jobs, created independently to run depending on the other. Currently there are two t-codes executed at the close of business 5:30PM:
T-code FPVA runs the dunning proposal then t-code FPVB executes the dunning run at 9:00PM
T-code EA20 is executed to run billing at 12:05AM
Invoicing runs at 1:00AM
Printing runs at 2:00AM
Is there a way that these can be scheduled to run depending on the other, ? Currently we use SM36 to schedule background jobs and SM37 to extract the information, but I don't know if ECC6.0 has the capability for this job?
Thanks in advance
Valentina