Hi Experts,
In the EA40 I receive an error message "error when reading in table EABP" (E9014).
move out is done on 12.07.2013 but later
Move out date and Stop date for budget billing request is changed from 12.07.2013 to 06.06.2013 .
First, print document is printed successfully but later it was reversed and the new print document which is created has "No print date".
I checked the payment scheme for the contract but it doesn't exist.
What is the possible reason for this error ?
Thanks in advance
Dushyant