Hello everyone,,
I am basically MM consultant, and we are to implement SAP for a utilities company.
the plan is:
Phase one: SAP utilities (DM, Billing, FICA and CRM) and FICO.
Phase two: SAP MM and other modules like PM....
My question is: is this valid implementing ISU without MM at the same time and postponing the MM until later (the company will work after phase 1 and then after a while the MM implementation starts).
I thought that MM is essential to have at the begging to at least define the devices for the DM, org structure, integration with FICO and so on.
I really appreciate the support here